Room with a view

February 29, 2008

We knocked out the bedroom windows. The window facing the neighbors house was blocked permenantly and this window was installed. It looks great and will be much nicer when the shed outside is moved. small-window.jpgsmall-window-outside.jpg


2/25 – 3/2

February 29, 2008

This weeks goals….finish wiring the back area. Put up sheetrock and start finishing the walls everywhere besides the bathrooms. …..the back area was wired and dana and I put up what sheetrock we had… about nine 12′ sheets.

Dana put up all the light boxes, fan and chandelier braces. 2/29/08


Kithen Footer

February 29, 2008

I dug the footer two weeks ago, that was fun, especially since there is only 3 feet to work with in the crawl space. Then the next day got ten bags of cement to fill it in. Turns out it took 21! bags, that was even more fun. But its done and ready.small-footer.jpgsmall-footings.jpg